Sakura

Overview

The total Project is a 75 unit townhouse development configured into 18 buildings and an amenity building in South Surrey’s Morgan Heights neighbourhood.

Results

During the construction of the Sakura residences, we managed to uncover hidden costs that had not been accounted for. The team was able to strategically allocate funds to cover these costs without exceeding the set budget. The total project was constructed in three phases over a period of 28 months within budget.

What Clients Say

My experience with ConEcon has been very positive. Really appreciate how accessible and prompt correspondence has been, as well as all responses to email requests and conducting inspections for progress claims on the Sakura townhouse project & the West Rosemary Heights subdivision. I would not hesitate to consult with ConEcon for quantity surveyor services on any future projects. Thank you for all your help.

Sham Sandhu ‒ Director, CastleHill Homes Ltd castlehillhomes.ca/